TC Energy is preparing for the next stage of its Coastal GasLink pipeline project, with construction of five new compressor stations expected to begin in 2027.
The company outlined its plans during a presentation to the Peace River Regional District board on Thursday, where community relations project advisor Heather Desarmia provided an update on the existing pipeline and the proposed expansion.
Desarmia said the 670-kilometre Coastal GasLink pipeline is already operational, carrying natural gas from Groundbirch in northeast B.C. to LNG Canada’s export facility in Kitimat.
She noted LNG Canada has shipped more than 100 cargoes since its first export shipment in June 2025.
During the first phase of construction, Desarmia said the project awarded more than $1.8 billion in contracts to local and Indigenous communities. It also generated the equivalent of more than 27,000 full-time jobs and saw over $13 million invested back into communities.
TC Energy now hopes to build on those benefits through Phase 2, which received financial approval from its joint venture partners at the end of September.
The expansion will add five compressor stations along the existing pipeline route, allowing more natural gas to move through the system.
The proposed locations are Sukunka Falls, Raccoon Lake, Clear Creek, Segundo Lake and Parrott Lakes. Desarmia said the company has used existing access roads and previously disturbed land wherever possible when identifying sites.
Once complete, the additional facilities are expected to increase the pipeline’s daily capacity from about 2.1 billion cubic feet to approximately 4.9 billion cubic feet.
Construction is expected to be carried out in stages rather than beginning at all five sites at once. However, Desarmia said there will be a period when work is underway at all five facilities simultaneously.
At peak construction, TC Energy expects more than 2,100 people to be working across the five sites.
The company also plans to hold information sessions ahead of construction to connect local job seekers, contractors and business owners with the project’s future prime contractors.
Temporary workforce accommodations are also expected, similar to those used during Phase 1, so workers can walk between their lodging and job sites.
During the presentation, Electoral Area C Director Allen Courtoreille asked about the number of permanent positions the new compressor stations could create.
Desarmia said the company is estimating between six and 10 full-time jobs per facility, although the final numbers will depend on each site’s size, scope and location.
She also told directors the existing Coastal GasLink pipeline generates about $25 million in annual property tax revenue for the province. Of that, approximately $5 million goes to the Peace River Regional District, with another $11 million coming from TC Energy’s NOVA Gas Transmission Ltd. assets in the region.
Desarmia said Phase 2 is expected to generate additional tax revenue.
TC Energy says it will continue providing updates as planning moves forward, including further community presentations before construction begins.