City officials say they are moving into the next phase of planning for a long-term water supply, as concerns about drought and river levels continue to shape the community’s future.
The City of Dawson Creek is launching more detailed technical studies to determine where future water will come from, how much will be needed and how it will be delivered — decisions that could affect residents, industry and development for decades.
The work follows early engagement last fall through the B.C. Environmental Assessment Office, which highlighted the urgency of securing a stable supply.
For residents, the outcome could influence everything from water restrictions during dry seasons to the cost of infrastructure upgrades.
The city said the latest phase will examine potential water sources, treatment requirements, infrastructure routes and the costs tied to each option. Officials also plan to consult Indigenous communities, regulators, local industry and residents before narrowing in on a preferred solution.
“The Water Supply System Project is focused on creating a long-term and reliable drinking water solution for Dawson Creek and the region. As we move forward, we’re undertaking more technical work and engagement with Indigenous communities, government and regulatory agencies, industry and residents to ensure our decisions are based on evidence and aligned with community values. By better understanding how much water we need, where we can source the water from, and the costs and challenges of each option, we can choose the best path forward for our community’s future.” said Devon Aaroe, general manager of major infrastructure and development, City of Dawson Creek
The broader project will unfold in four phases, from early research to implementation planning, giving the city time to adjust as new information emerges.
In the short term, Dawson Creek is also continuing work on a temporary emergency overland water transfer system. The system is designed to be deployed during severe drought or low river flow, offering a backup supply under a provincial approval agreement.
City council received an update on the project at its March 30 meeting. Officials say more public updates are expected as technical work continues.
For more information, visit dawsoncreek.ca/water-supply.